PV Power Plant  Templin, Germany

Maximum reliability with SUNNY CENTRAL 900CP XT

Europe’s largest thin-film PV power plant in Templin

Equipped with 114 Sunny Central 900CP XT inverters, Europe’s largest thin-film PV power plant was commissioned in Templin, Brandenburg/Germany. Due to their advanced grid management functions, SMA Sunny Central inverters were deemed the best choice for the 128 MWp project and its goal of providing renewable energy to the greater Berlin area.

In total, over 1.5 million thin-film modules from the manufacturer First Solar and 114 central inverters from the manufacturer SMA were installed in Templin. In a single year, the solar power plant generates more than 120 million kilowatt hours of power, which corresponds to the annual consumption of almost 36,000 households. This saves around 90,000 tons of the climate-damaging greenhouse gas CO2 every year.

Location
Templin, Germany

Commissioning
April 2013

Planning and realization
Belectric Solarkraftwerke GmbH

System size
128 MWp

Annual yield
120 million kWh
CO2 reduction: 90,000 t

Inverters
114 Sunny Central 900CP XT

Modules
1.5 million modules by First solar

Questions? Speak to an SMA expert

Contact

Discover more references

View all