Off-Grid System Serengeti, Tanzania

Camp in the Serengeti

Hybrid Energy Supply – Tanzania

Previously the camp was supplied by two 100kWp diesel generators running day and night at a high cost per month.

Now the camp is run by a 133 kWp PV field and a 900 kWh battery bank with the SMA Multicluster System incorporating Sunny Island battery inverters. During cloudy periods, the diesel gensets serve as backup, charging the batteries and simultaneously provide power. The SMA Multicluster System was the obvious choice for this system due to the reliability of the products given the remote location in Tanzania.

Location
Tanzania

Commissioning
2016

Plant information
Installed PV power: 133 kWp
Annual energy yield: 206,000 kWh

System Technology
15 Sunny Island 8.0H-11
6 SMA Sunny TriPower 20000TL-30
1 Multicluster Box 36